Flood protection for Kentuckians restored at Middlesboro levee

Dec. 26, 2023
Work to clear and reinforce the Middlesboro Flood Protection Project levee is completing, restoring the levee’s capacity and reinforcing its structure.

The U.S. Army Corps of Engineers (USACE) Nashville District announced that the Middlesboro Flood Protection Project’s levee channel has been fully cleared.

The work restores the levee’s capacity to protect Kentuckians, their homes, and local businesses and infrastructure from flooding after more than a decade of sediment build-up in Yellow Creek.

The community of Middlesboro sits in a crater formed by a meteorite. Surrounded by mountains, the city is prone to issues with runoff.

“Flooding is a huge issue here,” said Middlesboro Mayor Boone Bowling.

Yellow Creek and its tributaries flow through the heart of the city, bordered by its middle and high school campus, a church, the Bell County airport, businesses, and homes for some of Middlesboro’s more-than 9,300 residents.

When USACE’s planning for the channel clearing began in 2019, the budget was just $1.9 million, and the project’s scope only included removing sediment. In fiscal year 2021, an additional $4.2 million in Funding Pot funds were added.

“As things progressed…the Bipartisan Infrastructure [Law] was passed, leading to funding to do more robust channel clearing and to armor sections of the levee with concrete-filled articulated mats,” explained Michael Lapina, Eastern Kentucky Area operations project manager for the USACE Nashville District.

The Bipartisan Infrastructure Law’s additional $1.8 million brought the total for the 100 percent federally funded project up to $7.9 million.

Work began in December 2021 by USACE’s contractor, New York-based Mohawk Valley Materials. When it was completed in November 2023, they had removed a total 76,560 cubic yards of built-up sediment and vegetation and installed 19,360 square yards of the articulated mats.

The mats, placed just under the surface soil of the levee at critical points, greatly reduce the risk of structural failure if the levee is ever overtopped.

USACE worked with the Commonwealth of Kentucky to partner with Double Mountain Mining, helping the company reclaim their Middlesboro complex, and permit disposal of sediment from the channel at the mine site after testing to ensure it was free of contaminants.

“It was good material. You use it to reclaim a mine site – it’s a win-win situation,” Lapina said.

Flood damages prevented by the Middlesboro Flood Protection Project total an estimated $851 million since it was built by USACE in 1938. It remains the only federally funded levee in the USACE Nashville District’s Operations and Maintenance portfolio and has never failed in its 85 years of service.

With channel clearing complete, the capacity of the levee is restored, and its structure is re-enforced.